If I schedule a siding replacement now (mid-summer), when can I realistically expect it to start and finish? I live in Wayland and want to make sure the weather doesn't delay things too much. Is a two-week install normal, or is that overly optimistic?
top of page


bottom of page
We booked our project in July and siding in Wayland https://ubrothersconstruction.com/l-home-renovation-wayland was installed by mid-August. The contractor was clear about timing upfront and stuck to the estimated window almost to the day. It took them about 10 working days from start to finish, including removal of the old siding, prep work, and installation. What impressed us most was how efficient the crew was — they worked like clockwork, and even on hotter days, progress was steady. They managed the entire process professionally, and we had no issues with delays or rework.